Stock Photo - 16 December 2020, Mecklenburg-Western Pomerania, Tribsees: Work on the new bridge on the subsided A 20 Baltic motorway is in full swing, with traffic rolling over the temporary bridge on the left. A total of 308 bored piles are being driven into the ground for the almost 800-metre-long northern half of the bridge, 254 are already in the ground. Work began in April 2020 and is on schedule. The first half of the bridge is due to be completed in autumn 2021, with overall completion of the A20 scheduled for 2023. The motorway, built on a bog, had collapsed in autumn 2017. Photo: Bernd Wüstneck/dpa-Zentralbild/dpa. - Tribsees/Mecklenburg-Western Pomerania/Germany

Stock Photo: 16 December 2020, Mecklenburg-Western Pomerania, Tribsees: Work on the new bridge on the subsided A 20 Baltic motorway is in full swing.