Photo de stock - 16 January 2020, Mecklenburg-Western Pomerania, Neubrandenburg: View into the interior of the construction site of the new water reservoir for the so-called ""Power-to-Heat"" system. According to the public utility company (neu.sw), the water reservoir is to be filled with water on 27.01.2020. Just filling the almost 40-metre high reservoir, which holds 23 million litres of water, is expected to take 40 days. In the plant, the water is to be heated with surplus green electricity from wind energy, as in an oversized immersion heater, and fed into the district heating network. During this time, the natural gas power plant that is otherwise responsible for this can be shut down. A total of 14 million euros is to be invested. Photo: Stefan Sauer/dpa. - Neubrandenburg/Mecklenburg-Western Pomerania/Germany

Photo de stock: 16 January 2020, Mecklenburg-Western Pomerania, Neubrandenburg: View into the interior of the construction site of the new water reservoir for the so-called.